问题描述

您好,

我已经建立了一张地图,我的Excel数据被正确加载到Project中,关注的是它需要24分钟和计算分钟数。  Win7笔记本电脑上的Project and excel 2010。 CPU /内存性能未达到最大值。 我怀疑它是由
引起的,可能是从excel加载的前辈。 thx

I have established a map and my data from Excel gets loaded in to Project correctly, the concern is that its taking 24 and counting minutes.  Project and excel 2010 on a Win7 laptop. CPU/Mem performance are not maxed out.  I suspect it is caused by the may predecessors that load from excel. thx

推荐答案

您导入了多少数据(例如,任务数量,资源等)?另外,我建议您不要将前置任务导入Predecessor字段,而是将它们导入文本字段(例如Text1)或Notes字段,如果任何一个前驱字符串中有超过255个字符
。为什么?因为如果在加载新的前任时Project不必重新计算所有内容,导入会更快。在
设置基本任务数据后,您始终可以将前一个数据从Text或Notes字段传输到Predecessor字段。

How much data are you importing (e.g. number of tasks, resources, etc.)? Also I would recommend that you NOT import predecessors into the Predecessor field, rather import them into a text field (e.g. Text1) or the Notes field if there are more then 255 characters in any one predecessor string. Why? Because the import will go faster if Project doesn't have to re-calculate everything as a new predecessor is loaded. You can always transfer the predecessor data from the Text or Notes field to the Predecessor field after the basic task data is set up.

此外,我假设您没有尝试加载每个任务的开始和结束日期。您应该只导入基本数据(任务名称,持续时间,链接,资源,分配),然后让Project计算时间表。

Also, I assume you are not trying to load start and finish dates for each task. You should only import the basic data, (task name, duration, links, resources, assignments), and let Project calculate the schedule.

并关闭导入的自动计算。一切都被导入后再打开。

And turn off auto-calculation for the import. Turn it on once everything is imported.

John